Is New Jersey's Power Grid Running Short? What PJM's Shrinking Reserve Margin Means for Outages

Suburban New Jersey home at winter dawn with rooftop solar panels, a wall-mounted home battery, and high-voltage transmission lines on the horizon, illustrating PJM grid outage risk

Whether you're in PSE&G, JCP&L, Atlantic City Electric or Rockland Electric territory, your power runs on PJM, the 13-state grid that New Jersey shares with its neighbors. In PJM's last two capacity auctions, the PJM reserve margin (the cushion of extra supply kept above peak demand) cleared at 14.4%, short of PJM's 20% target. That is a real warning sign, but it is not a blackout forecast. Here is what the numbers mean for outages at your house, and how to plan without panic.

As of October 20, 2026: figures come from PJM's 2027/28 and 2028/29 capacity auction reports, NERC's January 2026 and May 2026 reliability assessments, PJM's preliminary July 2026 peak data, and DOE emergency orders. PJM's backstop auction has no new date yet.

At a glance:

  • Is NJ's grid running short right now? No. NERC rated PJM low risk for summer 2026, and PJM's record July 2 peak was served without rolling blackouts.
  • How far has the reserve margin fallen? PJM's last two capacity auctions cleared at a 14.4% reserve margin against a 20% target, about 6.5 GW and 6.8 GW short, per PJM's auction reports.
  • When does the risk peak? NERC rates PJM elevated risk for 2026โ€“2028 and high risk from 2029, with winter early mornings and evenings the riskiest hours.
  • What is driving it? Demand growth led by data centers, plus generator retirements and slow-arriving new projects, per NERC.
  • Which outage is more likely at my house? A local storm or equipment outage on your utility's wires, not a PJM supply shortfall.
  • Does home backup help in a grid emergency? Yes. A battery that can island, or a generator with a transfer switch, covers your essentials whatever caused the outage.



Suburban New Jersey home at winter dawn with rooftop solar panels, a wall-mounted home battery, and high-voltage transmission lines on the horizon, illustrating PJM grid outage risk
A New Jersey home with rooftop solar and a wall-mounted battery at winter dawn. NERC says PJM's greatest shortfall risk falls on winter early mornings and evenings.

Official sources (last checked: October 12, 2026):

  • U.S. Department of Energy, Order No. 202-26-40 (Eddystone Units 3 and 4; emergency determination for the PJM region) (order issued August 21, 2026)
  • PJM Interconnection, 2028/2029 Base Residual Auction Report (July 14, 2026)
  • PJM Interconnection, 2027/2028 Base Residual Auction Report (December 17, 2025)
  • North American Electric Reliability Corporation (NERC), 2025 Long-Term Reliability Assessment (January 2026)
  • North American Electric Reliability Corporation (NERC), 2026 Summer Reliability Assessment (May 2026)
  • PJM Interconnection, "PJM Serves Load Through Record-Breaking July Heat" (Inside Lines, July 10, 2026)
  • PJM Interconnection, "June Hot Weather Operations, June 29 โ€“ July 5" (Operating Committee presentation, July 9, 2026)
  • PJM Interconnection, 2026 Long-Term Load Forecast (Inside Lines summary, January 14, 2026) and Generation Interconnection Reforms update (June 4, 2025)
  • Monitoring Analytics (PJM Independent Market Monitor), Market Monitor Report (July 27, 2026) and Analysis of the 2025/2026 RPM BRA, Part G (June 3, 2025)
  • New Jersey Board of Public Utilities, press release on projected June 1, 2025 bill changes (February 12, 2025)
  • New Jersey Legislature, A796 [Third Reprint] (Senate amendments May 28, 2026)

Is New Jersey's Power Grid Running Short in 2026?

No, New Jersey's grid is not running short today: NERC rated PJM low risk for summer 2026, and PJM served a record July 2 peak without ordering load shed. But the reserve cushion PJM has bought for the 2027/28 and 2028/29 delivery years falls below its own 20% target. The honest summary is that the grid is tightening, not failing. This coming winter, the season NERC flags as riskiest, also falls inside its 'elevated' 2026โ€“2028 window, so 'not short today' does not mean 'no risk.'

New Jersey does not run its own power grid. It is part of PJM Interconnection, the regional grid operator for a 13-state grid, and supply and demand are balanced across that whole footprint. That is why the shortfall is measured across all of PJM, not state by state.

In PJM's 2028/29 auction, every zone cleared at the same capped price, including the capacity zones that cover New Jersey (PSEG, PS-NORTH, JCPL, DPL-SOUTH and EMAAC). There is no separate New Jersey shortage. New Jersey draws on the same regional pool as everyone else in PJM.

So what does a shortfall actually mean? PJM answers that directly in its 2028/2029 Base Residual Auction Report: "Such a shortage does not necessarily mean that the PJM system will be unable to serve load reliably in the delivery year; it means that PJM would have to operate with slimmer reserves and greater level of risk."

The real concern is the trend. Two auctions in a row have come up short, and NERC rates PJM elevated risk for 2026โ€“2028 and high risk from 2029. For most households, though, the outage you are likeliest to see is still a local one caused by a storm or failed equipment, which we cover later.

Claim: A capacity-auction shortfall is a warning about future risk. It is not a forecast that New Jersey will have blackouts.

Evidence: PJM's own 2028/29 auction report says the shortage "does not necessarily mean that the PJM system will be unable to serve load reliably," only that PJM "would have to operate with slimmer reserves and greater level of risk." NERC rated PJM low risk for summer 2026, and PJM met a preliminary all-time peak on July 2, 2026 without ordering load shed.

What Is the PJM Reserve Margin, and How Far Has It Fallen?

The PJM reserve margin is the extra supply PJM buys above its forecast peak demand, and its last two capacity auctions cleared at 14.4% against a 20% target. That left them 6,516.6 MW short for 2027/28 and 6,831.3 MW short for 2028/29.

A quick unit check: a megawatt (MW) is a measure of power, and 1 gigawatt (GW) equals 1,000 MW. So those gaps are about 6.5 GW and 6.8 GW, according to PJM's auction reports.

What the 20% cushion is for

The cushion exists because the grid never runs exactly to plan. Power plants break down, extreme weather pushes demand past the forecast, and forecasts themselves miss.

Two of those have happened recently. Between July 2 and July 4, 2026, forced outages (plants that were unexpectedly offline) ranged from 18,100 MW to 19,400 MW, according to PJM. And in summer 2025, PJM had forecast a normal summer peak of about 154,000 MW, but a June 2025 heat wave pushed actual load to more than 161,000 MW.

A thinner cushion leaves less room to absorb surprises like those, especially when they arrive together.

From above target to two shortfalls in a row

PJM buys capacity years in advance through an auction it calls the Base Residual Auction (BRA). The auction held in December 2025 bought capacity for the 2027/28 delivery year, and the one held in July 2026 bought capacity for 2028/29.

That timing matters. The 14.4% figure is the cushion PJM has lined up for those future delivery years. It is not today's reserve level.

What has changed is the direction. PJM's own summary table shows earlier auctions clearing above their targets, and the 2026/27 auction was roughly balanced. Then 2027/28 and 2028/29 both fell short. In PJM's words: "This is the second BRA in a row where PJM has cleared more than one percentage point below the IRM." IRM is PJM's installed reserve margin target, the 20% figure.

PJM reliability signals at a glance

Here is where the main reliability signals stand as of October 12, 2026. NERC's summer figure and the auction figures are calculated on different bases, so read each row on its own rather than comparing them with each other.

SignalLatest valueWhat it means for a New Jersey home
Reserve margin, 2027/28 capacity auction (Dec. 2025)14.4% vs a 20% target; 6,516.6 MW shortPJM bought a thinner cushion than it wanted for that delivery year. That means more risk, not a blackout forecast.
Reserve margin, 2028/29 capacity auction (July 2026)14.4% vs a 20% target; 6,831.3 MW short; second shortfall in a rowThe gap is not closing yet. PJM would run with "slimmer reserves and greater level of risk."
NERC long-term risk ratingElevated 2026โ€“2028; High from 2029Risk is rising over the next few years. It is not an emergency this week.
NERC summer 2026 ratingLow risk; about 26% installed reserves vs an 18.6% requirementThis summer's outlook was sound, but extreme heat still calls on demand response.
Highest-risk window (NERC)Winter, early mornings and eveningsPlan backup around heating-season mornings and evenings, not only summer heat waves.
Record peak, July 2, 2026168,158 MW, preliminary and unrestricted; prior record 165,563 MW (Aug. 2, 2006); no load shedThe grid held, but it took about 6,100 MW of emergency demand response and every available generator.
10-year demand forecastAbout 222,000 MW summer peak by 2036; 3.6%/yr growth vs 0.3%/yr in the 2021 forecastDemand growth, led by data centers, keeps pressure on supply.
Backstop procurement for new capacityAbout 6.8 GW; delayed after FERC's Sept. 29, 2026 order; no new dateThe main near-term fix for the shortfall is on hold.

Key takeaway: PJM's auctions have gone from clearing above target, per PJM's own summary table, to two shortfalls in a row, about 6.5 GW and 6.8 GW. That is the clearest sign the cushion is thinning, but it describes risk in future delivery years, not an outage forecast for your street.

Why Is PJM's Reserve Margin Shrinking?

PJM's reserve margin is shrinking because forecast demand is growing at its fastest pace in years, driven primarily by data centers, while generator retirements and project delays slow the arrival of new supply. Both sides of the balance are moving the wrong way at the same time.

Data centers lead the demand forecast

NERC puts it plainly in its 2025 Long-Term Reliability Assessment: "Demand for electricity in PJM is growing at its fastest pace in years, driven primarily by data centers, followed by electrification and manufacturing loads."

PJM's 2026 Long-Term Load Forecast projects a summer peak of about 222,000 MW in 2036, up nearly 66,000 MW over 10 years. That works out to average growth of 3.6% per year, compared with 0.3% per year in PJM's 2021 forecast.

The same pattern shows up in the auctions. Forecast load in the 2028/29 auction rose by 1,374.5 MW, "largely due to additional Large Loads," which is PJM's term for very large customers such as data centers. PJM's Independent Market Monitor reports that data-center load in the forecasts behind each auction grew from 7,927 MW for 2025/26 to 21,470 MW for 2028/29. Those are forecast figures, not metered use.

New Jersey is part of that picture. PJM's 2026 forecast lists the JCPL zone among the zones with data-center load growth, and it cites the PS (PSE&G) zone for "growth in data center load and port electrification."

Forecasts are not guarantees, though. PJM trimmed the near-term years of its 2026 forecast after stricter vetting of data-center requests, cutting 2028 by 2.6%. And while the Independent Market Monitor calls data-center load growth "the primary reason" for recent capacity market conditions, it adds that PJM might eventually have reached a tight supply and demand balance anyway, but on a relatively slow trajectory that would have left more time for the market to respond.

Retirements and project delays on the supply side

On the supply side, NERC warns that "PJM faces an extreme and rapid tightening of capacity resources in the near term because of generator retirements and project delays." In plain terms, plants are retiring while new projects take longer than planned to come online.

One example: Units 3 and 4 at the Eddystone plant in Pennsylvania were scheduled to retire on May 31, 2025, and have been kept available since then by rolling federal emergency orders, covered below.

Tight supply also shows up on bills: the 2025/26 capacity price jumped from $28.92 to $269.92/MW-day, and the NJBPU said "PJM's recent capacity auction results are the main driver" of the average residential bill increases of 17.23%โ€“20.20% it projected from June 1, 2025.

Where the interconnection queue stands

New supply has to clear PJM's interconnection queue, the study process a new generator goes through before it can connect to the grid. As of June 2025, PJM reported that about 63,000 MW of a roughly 200,000 MW transition backlog remained, with all transition projects to be processed by the end of 2026 and a new application cycle set to open in spring 2026.

NERC's more recent snapshot, from January 2026, counts approximately 30,000 MW of generation projects in the transitional queue to be processed in 2026. Separately, PJM's one-time Reliability Resource Initiative accepted 51 projects totaling more than 11,000 MW of "shovel-ready" natural gas, nuclear and battery capacity.

Keep one caveat in mind. "Processed" means studied and moved through the queue. It does not mean built and running.

Claim: Data centers are the main reason PJM's demand forecast jumped, but forecast load is not guaranteed load, and PJM is already trimming speculative requests.

Evidence: NERC says PJM demand growth is "driven primarily by data centers," and PJM's 10-year growth rate is now 3.6% a year versus 0.3% in its 2021 forecast. PJM also cut its 2028 forecast by 2.6% after stricter vetting of data-center requests, so the outlook shifts as projects prove real or fall away.

When Is Outage Risk Highest for New Jersey: Which Years and Which Season?

NERC rates PJM elevated risk for 2026โ€“2028 and high risk from 2029, and it says the greatest shortfall risk falls in winter, during the early-morning and evening hours. That combination tells a New Jersey, including in New Brunswick, household both when to have a plan in place and which hours to plan around.

Elevated now, high from 2029

NERC's 2025 Long-Term Reliability Assessment, published in January 2026, labels PJM "Elevated Risk 2026โ€“2028 | High Risk 2029โ€“." It projects that PJM's anticipated reserve margin may fall below its required level in 2029.

Elevated is a step below high on NERC's scale, and NERC's rating for PJM moves from elevated to high in 2029. An elevated rating is not a prediction that an emergency is coming this week.

Why winter mornings and evenings matter most

NERC is specific about timing: "The greatest risk of resource shortfalls leading to unserved energy or load loss in PJM occurs in the winter months during the early morning and evening hours."

NERC's summary does not spell out the reasons, but general reasoning points to two. Heating demand climbs on cold mornings and evenings, and solar panels, on rooftops and on the grid, produce nothing before sunrise or after sunset.

For a household, a winter outage is mostly a heat problem. Most gas and oil furnaces and boilers still need electricity to run their blowers, pumps and controls, so losing grid power can mean losing heat even with a full fuel supply. If that describes your home, it pays to plan backup for HVAC, refrigeration, and daily essentials before heating season.

Why summer 2026 was rated low risk

NERC's 2026 Summer Reliability Assessment, released in May 2026, rated PJM low risk for the summer, with about 26% installed reserves against an 18.6% requirement. That is a near-term, current-season measure calculated differently from the auction's 14.4%, so the two should not be compared directly.

Even so, NERC noted: "If extreme high temperatures are experienced, PJM anticipates the need for demand-response resources to help reduce load." That is exactly what happened in early July.

Claim: A New Jersey household that wants to be ready for a grid shortfall should plan around cold winter mornings and evenings, not only summer heat waves.

Evidence: NERC's 2025 Long-Term Reliability Assessment says the greatest risk of resource shortfalls in PJM "occurs in the winter months during the early morning and evening hours," while it rated PJM low risk for summer 2026. Those winter hours are dark, so rooftop solar is not producing, and they are when heating systems that need electricity are working hardest.

What Happened During PJM's Record Peak on July 2, 2026?

On July 2, 2026, PJM met a preliminary all-time peak of 168,158 MW (unrestricted) without ordering load shed, but only by calling about 6,100 MW of emergency demand response, running every available generator, and using a federal emergency order that waived emissions limits. It is the clearest recent picture of what a thin cushion looks like in practice.

High-voltage transmission lines and a substation near New Jersey suburbs on a hot, hazy summer afternoon, representing PJM's record July 2026 peak demand
Transmission lines on a hot summer afternoon. PJM met a preliminary, unrestricted all-time peak of 168,158 MW on July 2, 2026 without ordering load shed.

How the record compares

PJM reports that load peaked at an estimated 168,158 MW between 5 and 6 p.m. on July 2, 2026. That is a preliminary, unrestricted figure, and it topped the previous record of 165,563 MW set on Aug. 2, 2006.

You may see two numbers for that day. PJM's preliminary instantaneous (metered) peak was 162,713 MW at 5:55 p.m. The unrestricted 168,158 MW figure is higher because it adds back the load that demand-response programs took off the system. Both are preliminary.

PJM says it "maintained reliable operations July 2 through a preliminary energy use record, requiring all available generation to keep the power flowing."

The emergency steps PJM took

Between June 29 and July 5, 2026, PJM worked through several stages of its emergency procedures. NERC labels these stages with Energy Emergency Alert (EEA) levels. According to PJM's Operating Committee summary, the steps were:

  • A Maximum Generation Alert / Load Management Alert (NERC EEA1), a heads-up to generators and grid participants.
  • Pre-emergency and emergency load-management reductions (NERC EEA2), in which demand-response participants cut their use: about 6,113 MW on July 2 and 5,037 MW on July 3, per PJM's preliminary estimates.
  • A Maximum Generation Emergency Action.
  • "Deploy All Resources" for transmission security in the BGE, Pepco and Dominion zones only, not in New Jersey's zones.

The strain was real. Forced generation outages ranged from 18,100 MW to 19,400 MW between July 2 and July 4, and PJM used every single generator available on July 2. PJM's own assessment: "Our capacity position continues to be an area of concern."

The federal emergency orders behind the scenes

During the heat event, the U.S. Department of Energy issued two emergency orders under Section 202(c) of the Federal Power Act. One waived emissions limits, and about 3.25 GW was used under it.

The other allowed PJM to curtail data centers and other large loads that have their own backup generation. According to PJM, "The latter action was not needed and was never issued." In other words, that authority existed on paper, but no data centers were curtailed under it.

Claim: The record day shows the grid held, but with very little cushion left to spare.

Evidence: PJM says it maintained reliable operations on July 2 while "requiring all available generation." It also leaned on about 6,113 MW of preliminary demand response and a DOE emissions-waiver order, all while 18,100 MW to 19,400 MW of generation was unexpectedly offline. PJM itself called its capacity position "an area of concern."

What Are Regulators Doing to Close PJM's Shortfall?

Regulators are leaning on two stopgaps: U.S. Department of Energy emergency orders that keep a retiring Pennsylvania plant available, and a one-time PJM backstop auction for about 6.8 GW of new capacity that was delayed after FERC's September 29, 2026 order. Neither one has added a new power plant yet.

The first stopgap is a federal emergency order. Units 3 and 4 at Eddystone, a Pennsylvania power plant in PJM, are 380 MW each and run on natural gas or oil. They were scheduled to retire on May 31, 2025, and rolling 90-day orders under Section 202(c) of the Federal Power Act have kept them available since May 2025.

The latest, Order No. 202-26-40, was issued August 21, 2026, and runs from August 23 through November 20, 2026. In it, DOE determined "that an emergency exists in the PJM Interconnection, L.L.C. (PJM) region ... due to a sudden increase in demand, a shortage of electric energy, a shortage of facilities for the generation or transmission of electric energy, and other causes." The order also states that rate recovery is available for the costs. It is linked in the sources list at the top of this article.

The second stopgap is a one-time backstop auction. After the 2028/29 shortfall, PJM filed a Reliability Backstop procurement to buy about 6.8 GW of new capacity. On September 29, 2026, the Federal Energy Regulatory Commission (FERC) approved only parts of the plan, including a $555/MW-day offer cap, and found PJM "failed to adequately show" that its cost-allocation plan was just.

As reported by Utility Dive, PJM then delayed the auction, which had been set for September 30 to October 21, 2026, saying "A new timeline for the backstop procurement is yet to be determined." As of October 12, 2026, there is no new date, and who pays for the backstop is still unresolved.

Some new supply is already moving through the pipeline. The Reliability Resource Initiative's 51 accepted projects, totaling more than 11,000 MW, are a real step forward. But they are accepted projects, not power plants already online.

Claim: So far, the fixes buy time rather than add new power plants.

Evidence: DOE has extended the Eddystone units 90 days at a time since May 2025, with the current order running through November 20, 2026, according to DOE Order No. 202-26-40. The backstop auction meant to add about 6.8 GW of new capacity was delayed after FERC's September 29, 2026 order, with no new date set.

Grid Shortfall or Local Storm: Which Outage Is a New Jersey Home More Likely to Face?

A local outage on your utility's wires (storms, falling trees, failed equipment) is the more common outage for a New Jersey home. A PJM supply shortfall did not cause load shedding even on the record July 2026 peak.

What a PJM grid emergency looks like from your house

Grid emergencies generally escalate in stages: alerts to generators and grid participants first, then demand-response calls, then maximum-generation and other emergency actions. PJM's steps from June 29 to July 5, 2026 followed that ladder and stopped short of load shed.

From your kitchen, most of that ladder is invisible. Alerts and demand-response calls normally change nothing at your meter unless you have enrolled in a program that asks you to cut use.

Controlled rotating outages are the last resort. If the grid operator ever directed them, your own utility, whether PSE&G, JCP&L, Atlantic City Electric or Rockland Electric, would carry them out on local circuits.

Why storms remain the bigger day-to-day threat

Most outages New Jersey homes experience start on the local distribution system, the poles, wires and transformers serving your street. Nor'easters, summer thunderstorms, falling trees and equipment failures are the usual causes, not a regional supply shortfall.

Either way, the result at your house is the same: grid power stops at the meter. One note for solar owners: a standard grid-tied array shuts down in any outage, which is why most solar panels shut off during a blackout unless they are paired with a battery or other equipment that can island from the grid.

Who gets curtailed first under New Jersey's data-center bill

New Jersey's data-center tariff bill, A796, which was reported signed in July 2026, directs the BPU to "ensure the priority curtailment of large data center customers before residential customers, excluding designated critical load, under system emergencies." The BPU's standards are still to come, due within 12 months of the law taking effect, so this is not yet a guarantee that homes stay on first.

Put simply, a grid emergency serious enough to cut power at your meter is rare and regional. Storms are the everyday reason to have backup.

Claim: A home that is ready for a nor'easter outage is already ready for a grid emergency.

Evidence: Whether the cause is a downed line on your street or a utility-run rotating outage (the last step after alerts, demand response and maximum-generation actions), the result at your house is the same: grid power stops at the meter. A battery that can island from the grid, or a generator with a proper transfer switch, serves your backed-up circuits regardless of why the grid went down.

How Should a New Jersey Household Plan Backup Power for a Tighter Grid?

To plan backup for both storm outages and rare grid emergencies, follow 6 steps: list your essential loads, plan for winter heat, choose a battery, a generator, or both, confirm the system can island from the grid, keep it charged or fueled, and recheck the plan each fall. None of it requires guessing when PJM's next tight day will come.

Wall-mounted home battery and backup-loads subpanel beside a furnace in a New Jersey basement on a winter evening, set up to keep heating and essentials running during a grid outage
A home battery wired to an essentials panel beside the furnace. NERC rates PJM elevated risk for 2026โ€“2028 and high risk from 2029.
  1. List your essentials. Write down what must keep running during an outage: refrigerator, sump pump, furnace or boiler controls and blower, well pump if you have one, internet, any medical devices, and some lights.
  2. Plan for winter heat first. NERC's highest-risk window for PJM is winter mornings and evenings, so check whether your heating system needs electricity to run. Most gas and oil furnaces and boilers do.
  3. Choose a battery, a generator, or both. A battery is quiet, needs no fuel, and can recharge from solar. A generator offers long runtime as long as fuel lasts, but it needs regular maintenance, must run outdoors, and requires carbon monoxide precautions. Our guide to choosing a home battery or standby generator walks through the trade-offs, and many homes pair the two.
  4. Confirm the system can island from the grid. A battery needs a backup gateway or transfer equipment to run your home during an outage, and a generator needs a properly installed transfer switch. Solar panels on their own will not keep the lights on.
  5. Keep it charged or fueled. Set a sensible backup-reserve level on your battery, and keep generator fuel and its exercise schedule current. When a severe heat wave or cold snap is in the forecast, charge the battery to full ahead of time.
  6. Recheck the plan each fall. Review it before heating season, since winter is NERC's highest-risk window and its rating for PJM rises from elevated to high in 2029.

Size the plan around your essential circuits rather than the whole house. That keeps a battery's stored energy focused on what matters, and it keeps a generator from working harder than it needs to.

Key takeaway: Build your backup plan for the outage you are most likely to see, a local storm, and you will also be covered for the rarer grid emergency NERC warns about. Start with winter heating loads.



Frequently Asked Questions About PJM Grid Reliability and Outage Risk in New Jersey

What does a reserve margin actually measure on the power grid?

A reserve margin measures how much extra supply a grid operator has lined up above its forecast peak demand. PJM's target is 20%, and its last two capacity auctions cleared at 14.4%, according to PJM's auction reports.

That extra supply is there for the moments when several things go wrong at once. Between July 2 and July 4, 2026, for example, 18,100 MW to 19,400 MW of generation was unexpectedly offline during a record heat event, per PJM.

Can rolling blackouts happen in New Jersey if PJM runs short of power?

Yes, but only as a last resort, after alerts, demand-response calls and maximum-generation actions have been used. In that case, your local utility would carry out controlled rotating outages on local circuits at the grid operator's direction.

It has not come to that. PJM did not shed load even on its record July 2, 2026 peak, and PJM says a shortfall means operating "with slimmer reserves and greater level of risk," not necessarily that it will be unable to serve customers reliably.

What does a PJM grid alert mean for my household?

A PJM grid alert is a heads-up to generators and other grid participants, and on its own it changes nothing at your meter. During the June 29 โ€“ July 5, 2026 heat event, for example, PJM issued a Maximum Generation Alert / Load Management Alert, which NERC classifies as EEA1.

If you are enrolled in a demand-response program, you may be asked to cut your use. Otherwise, treat an alert during extreme heat or cold as a practical reminder to top off your battery and check your generator fuel.

Is New Jersey's power grid more at risk in winter or in summer?

Winter. NERC's 2025 Long-Term Reliability Assessment says "the greatest risk of resource shortfalls leading to unserved energy or load loss in PJM occurs in the winter months during the early morning and evening hours."

Summer 2026 was rated low risk, though extreme heat still leaned on demand response. PJM's preliminary estimate is about 6,113 MW of demand response on July 2.

How soon could PJM's reserve shortfall start to affect reliability?

NERC already rates PJM elevated risk for 2026โ€“2028 and high risk from 2029, when it projects PJM's anticipated reserve margin may fall below the required level.

The auction shortfalls apply to the 2027/28 and 2028/29 delivery years. The backstop auction meant to add about 6.8 GW of new capacity was delayed after FERC's September 29, 2026 order and had no new date as of October 12, 2026.

Does a home battery help during a PJM grid emergency, or only during storm outages?

A home battery helps in both, because it does not care why grid power stopped. If it is installed with backup (islanding) capability, it powers your backed-up circuits during a storm outage or a utility-run rotating outage alike.

How long it lasts depends on how much energy it stores and what you run. Our guide to how long a home battery can run your house covers runtime in more detail.

Your Next Step for Grid-Outage Readiness in New Jersey

The grid is tightening, storms are still the likelier outage, and the right move for most New Jersey homes is a backup plan built around winter essentials. Neither the auction numbers nor NERC's ratings call for panic, but together they are a good reason to have your plan in place before heating season.

Powerlutions designs and installs home battery backup across New Jersey, including Tesla Powerwall 3, FranklinWH and Enphase systems, and we size each system around your essential circuits and heating equipment. A good first step is a backup-loads review: what must stay on during a winter-morning outage, and whether a battery, a generator, or both fits your home.

Call 732-987-3939 or email info@powerlutions.com to set up your review, or use the buttons at the top of this page.

Why our clients feel weโ€™re a ray of sunshine

  • "Extraordinary"

    Powerlution is a professional company!!! They guided me from beginning to end ... I cant believe that its already 18 months since installation of my solar system and they are still available with any help or questions and concerns I have... I would definitely recommend powerlution... They are.... Professional, Helpful, Prompt, Reliable, Responsible, Honest

    โ€“ Fried Z.
  • "Extraordinary"

    Powerlution is a professional company!!! They guided me from beginning to end ... I cant believe that its already 18 months since installation of my solar system and they are still available with any help or questions and concerns I have... I would definitely recommend powerlution... They are.... Professional, Helpful, Prompt, Reliable, Responsible, Honest

    โ€“ Fried Z.

Zero $ out
of pocket

Max credits
incentives

Honest &
transparent

Proven solar experience since 2008

Get expert solar guidance today.

Call Now

Experience success on a solar level.

See Savings

Letโ€™s customize your solar plan.

Complete this form to:

1. Estimate savings on your energy use 2. Leverage the best state incentives

Footer Contact Form

Ready to explore your future setup?

Try our Layout Design Tool!

PowerLutions Solar Company - Solar
Installers in NJ, NY, FL, CT & MA

PowerLutions LLC

NJ Electrical Contractor 
Business Permit #17356
216 River Ave Lakewood, NJ 08701

MAIN OFFICE

216 River Avenue
Lakewood, NJ 08701
732-987-3939

NEW JERSEY

2 University Plaza #100-1
Hackensack, NJ 07601
201-624-9696

NEW YORK

56 South Main St Suite #2
Spring Valley, NY 10977
845-553-7100

NYC

1310 Coney Island Ave
Brooklyn, NY 11230
718-502-3200

MIAMI FLORIDA

66 West Flagler Street
Suite 900-3747
Miami, FL 33130
786-732-3306

Copyright © 2026.
Powerlutions Solar Energy
888.SUN.4.ENERGY